For the Bemidji-Grand Rapids line. Return to article.
April 2, 2008 |
Office of Energy Security recommends establishing an advisory task force |
5064019 |
April 24, 2008 |
PUC Order to establish an advisory task force |
5138381 |
June 4, 2008 |
Application for a Route Permit for the Bemidji to Grand Rapids 230 kV Transmission Line Project |
5264771 |
June 18, 2008 |
Office of Energy Security comments and recommendations |
5288689 |
June 30, 2008 |
PUC accepts application, authorizes, public advisor and agrees to com bine environmental review for certificate of need and route permit |
5313920 |
July 23, 2008 |
PUC Notice of Public meetings |
5373485 |
Sept. 24, 2008 |
Office of Energy Security Final Advisory Task Force Report |
5522683 |
April 3, 2009 |
OES Notice of scoping decision and intent to prepare an EIS |
5849110 |
Oct. 23, 2009 |
Office of Administrative Hearings First Prehearing Order |
200910-43184-01 |
Dec. 28, 2009 |
Office of Administrative Hearings Second Prehearing Order |
200912-45408-01 |
Jan. 27-28, 2010 |
Testimony from Utilities |
20101-46493-08* |
Feb. 11, 2010 |
OES Notice of Revised EIS Scoping Decision |
20102-46991-01 |
Feb 25, 2010 |
OES Draft EIS text (Accompanying documents contain maps) |
20102-47440-06 |
March 26, 2010 |
Office of Administrative Hearings Third Prehearing Order |
20103-48064-01 |
April 6, 2010 |
OES Notice of Public Hearings |
20104-48851-01 |
July 29, 2010 |
Office of Administrative Hearings Fourth Prehearing Order |
20107-53045-01 |
Sept. 2, 2010 |
OES Final EIS text (Accompanying documents contain maps and appendices) |
20109-54088-01 |
Sept. 20, 2101 |
Office of Administrative Hearings Order Finding of Facts, Conclusions and Recommendations |
20109-54602-01 |
Oct. 19, 2010 |
Route Map Index |
2010-55592-02 |
Nov 5, 2010 |
PUC Order accepts ALJ report (Accompanying documents contain maps) issues Route Permit |
201011-56255-01 |
Dec. 13, 2010 |
OES Revised Fact Sheet “Rights-of-way and Easements for Energy Facility Construction and Operation” |
201012-57391-01 |
Feb. 28 2011 |
Leech Lake requests PUC suspend or revoke Route Permit |
Not Seen |
March 23, 2011 |
OES recommendation regarding route variance |
20113-60546-01 |
March 25, 2011 |
OES Comments on request to revoke or suspend Route Permit |
20113-60603-01 |
March 31, 2011 |
PUC Public Comments |
20113-60792-01 |
April 21, 2011 |
Energy Facility Permitting Staff comments on request to revoke or suspend Route Permit |
20114-61579-01 |
April 27, 2011 |
Energy Facility Permitting Staff comments on route alignment changes |
20114-61846-01 |
May 5, 2011 |
Leech Lake Band of Ojibwe petition to revoke or suspend Route Permit |
20115-62315-01 |
May 26, 2011 |
PUC Staff Briefing Paper |
20115-62971-01 |
July 27, 2011 |
PUC accepts compliance filings |
20117-64665-01 |
June 29, 2012 |
Leech Lake Band of Ojibwe withdraws petition to revoke Route Permit |
20126-76295-01 |
July 6, 2012 |
Notice of Energization of the Boswell to Cass Lake portion of line |
20127-76545-01 |
Sept 11, 2012 |
Notice of Energization of the Cass Lake to Wilton portion of line |
20129-78588-01 |